Sydney Water is undertaking a major upgrade of the previously decommissioned Ryde-Pymble drinking water pipeline. This original pipeline was built in 1936 and ran from the Sydney Water Ryde Pump Station on Victoria Road to Roland Avenue in Wahroonga. It was disconnected from the network in 2014 due to its age and condition.
The new pipeline will basically follow the route of the old pipeline but will be wider at 900 mm compared to the 600 mm width of the old pipes. An existing pipeline is wide enough to be used from Roland Avenue down via Rothwell Road and Monteith Street up to Kissing Point Road (KPR). The new pipeline will then follow KPR and go under Browns Waterhole through a tunnel and then continue through Marsfield to the historic pumping station in Ryde.
Sydney Water needs areas for storage of pipes, supplies and equipment. There has been a consultation process run by Ku-ring-gai Council about the sites chosen and the council has to give approval for this use of council land.
The main site will be on the vacant land along KPR between Vernon and Saddington Streets. One other is in Yeramba Street reserve. The original plan for a compound at the end of Kate and Tamboon Streets has been dropped after objections based on proximity to houses, chemical leakage risks to the nearby forest land in Rofe Park and its bushfire risk category.
Impacts on Kissing Point Road
The old pipe runs under KPR on the southern side. The new pipe will be installed under the northern side. The contractor, McConnell Dowell will use a mix of open trenching and trenchless methods.
There will be significant traffic disruptions especially during peak hours and school drop off and pick up times near Turramurra Public School. Some detours and changes to bus routes will be needed. The project is predicted to take 12 to 18 months.
Sadly, all this means that many trees along the northern side of the road will either need to be removed if the trench impacts on a tree‘s root ball, or trimmed so the large trucks and excavators can operate. Certainly, the branches of trees hanging over the road will have to be pruned.
Planning approval
The project is being assessed under Part 5 of the Environmental Planning and Assessment Act 1979 (NSW). Sydney Water, as the delivery authority, is responsible for preparing and determining the Review of Environmental Factors including measures to manage environmental impacts as detailed in the Biodiversity Assessment Report.
The initial report prepared in September 2025 identified impacts of trimming or removal of native vegetation of 0.6 hectare and threatened ecological communities of 0.06 hectare (600 m2). This translated to 89 native remnant trees being affected plus 11 hollow bearing trees.
Currently a detailed assessment of all the trees along KPR is being undertaken. So far a large number of additional trees has been identified for pruning or removal. A statement made on 29 June referred to a further 159 trees to be removed and 288 to be pruned. An addendum to the Review of Environmental Factors Biodiversity Assessment is being prepared.
Affected trees are marked so that interested residents can identify them. There has been a lot of pushback about the trees loss — to council and Sydney Water by concerned residents and on social media.
Click here for maps of potential affected trees in sections along KPR.
This additional vegetation is a combination of non-threatened native vegetation and trees, hollow-bearing trees and some threatened native species. The exact impact on each of these, will be identified in the Review of Environmental Factors addendum.
Biodiversity management
The Biodiversity Assessment report prepared by Aurecon makes these statements about flora and fauna damage mitigation measures:
- qualified arborists and ecologists will inspect trees prior to and during works
- fencing will protect trees to be retained
- native vegetation to remain will be clearly delineated as no-go-zones to avoid risk of clearing
- fauna spotter catcher must be present during all construction works to avoid potential direct impacts to native species
- removal of wildlife, if required, will be undertaken by a qualified ecologist
- weed management controls and safeguards will be created before works starts
- dust suppression techniques (eg water sprays) and scheduling of noisy works will be implemented to minimise community disruption
- offsetting of tree loss will be carried out using a ratio of 2 for 1 native tree removed and 3 for 1 threatened species removed
- revegetated areas and trees planted must be monitored so that their survival until establishment is achieved
Tree replanting
Sydney Water will have a replanting scheme — not just with shrubs and tube stock but with substantial plants. At the information session on 7 July they asked for suggestions of where trees can be planted. We are welcome to send in suggestions in consultation with Ku-ring-gai Council. We don’t want the offsetting to be well away from the affected area as often occurs.